Driveway Repaving Update - Week of October 30
On Monday 10/31, expect milling and base repair between Kent and Heather Roads (marked in white on the construction schedule)
On Tuesday, 11/1, paving of part of Taylor Drive (marked in red on the map) will take place.
On Tuesday, Wednesday and Thursday (11/1, 11/2 and 11/3) expect continued milling and base repair between Carter Road, Heather Road and Taylor Drive (areas marked in pink on the construction map)
On Thursday and Friday (11/3 and 11/4) expect milling and base repair between Carter Rd, Edwards Rd and Taylor Drive in the areas marked with navy blue on the construction map.
Rain showers may delay repaving somewhat and the expected work could be slightly delayed.